Procurement claim against Department for Education over schools construction framework not time-barred, High Court judge rules
- Details
A High Court judge has ruled that a claim against the Department for Education over tender evaluation during the procurement of one lot of a £15bn+ schools construction framework agreement is not time-barred.
Bouygues (UK) alleges that the DfE’s tender evaluation for lot 2 of Construction Framework 25 was unlawful.
The procurement was conducted pursuant to the Procurement Act 2023.
On 5 December, the DfE issued an assessment summary to Bouygues (UK) saying it had been unsuccessful in the procurement. Its tender was ranked 11th with a score of 74.67. The lowest-placed successful supplier was 10th with a score of 74.8.
The claim form in the proceedings bears the issue date 5 January 2026, which was a Monday.
The DfE pleaded a limitation defence, to the effect that the time limit for commencing proceedings expired on 3 January, a Saturday, which the defendant argued was the last day of the 30-day period for commencing proceedings which is prescribed by s.106(2) of the 2023 Act.
Bouygues (UK) maintained that the proceedings were commenced within time and, in the alternative, sought an extension of time.
There was a further issue between the parties as to whether certain claims contained in the Re-Amended Particulars of Claim were subject to a later limitation period and were, in any event, within time.
In September 2026, Eyre J directed a trial of three preliminary issues, as follows:
“1. Whether any of the Claimant’s claims are time-barred under section 106(2) of the Procurement Act 2023 and if so which claims?
2. If the answer to question 1 is yes, whether the allegations pleaded [at various paragraphs] in the Amended Particulars of Claim comprise different causes of action which were subject to a different limitation period such that they are not time-barred?
3. In respect of any claims found to be time-barred, should an extension of time be granted under section 106(3) of the Procurement Act 2023 for the reasons pleaded by the Claimant?”
In Bouygues (U.K.) Limited v Secretary of State for Education [2026] EWHC 2998 (TCC) Mr Justice Coppel concluded on Issue 1 that the common law rule, known as the Kaur principle –after Pritam Kaur v S Russell & Sons Ltd [1973] QB 336, whereby a limitation period which ends on a “dies non”, on which the Court office is closed, will be extended to the next day that the office is open – applied to s.106(2) of the 2023 Act “such that the limitation period expired on 5 January 2026, the first working day after the end of the 30-day period in s. 106(2), which was on 3 January 2026”.
Mr Justice Coppel also said that there was “no inconsistency between the date of issue for limitation purposes being the date of submission of a claim form via CE-File and my earlier conclusion that the Kaur principle is applicable to extend the limitation period to the next working day”.
He continued: “The Kaur principle is applicable because it is not sufficient to commence proceedings under the Act to submit a claim form along with the fee; proceedings are only commenced when the claim form is accepted and issued by the court office, which cannot be done on a non-working day.
“But once that has been done, the effect of the Rules is that the date of commencement is deemed to be the date of submission of the claim form along with the requisite fee (if earlier than the date on which the claim form is actually issued). These conclusions can co-exist and there are good reasons of policy and authority for each.”
The claimant’s claims were not time-barred, Mr Justice Coppel concluded.
Turning next to Issue 3, the judge said that if proceedings had been commenced after the expiry of the s.106(2) limitation period, he would have granted Bouygues (UK) an extension of time. “I consider that, as in Amey, it would be ‘sterile and potentially unjust’ not to grant the short extension of time which would be necessary in this case in the event that I am wrong in my conclusions on Issue 1(b).”
Having earlier noted that no automatic suspension had been triggered, Mr Justice Coppel said: “This is an important Framework in terms of its value and the Claimant’s witnesses provided evidence about the impact upon it of not having won a place on the Framework. However, the Framework has been concluded and – although there remains some dispute between the parties about this, and I of course make no final determination – it is, at best, far from clear that the Claimant will be able to secure relief which requires its appointment to the Framework, and more likely that its remedy will be in damages.
“Even if the Claimant were to succeed in obtaining a ‘set-aside’ remedy (see s.104(2)(a) of the Act), the likely outcome would be a re-tender rather than the appointment of the Claimant to the Framework. I am not in a position to assess how valuable a damages claim might be and what impact securing damages might have on the Claimant or indeed the prospects of the Claimant securing appointment on a re-tender.”.
Mr Justice Coppel said that if the answer to Issue 1 was ‘yes’ and the answer to Issue 3 was ‘no’, he would have found that the claimant’s claims of breach of record-keeping and disclosure obligations and of invalidity of the Assessment Summary which relied upon alleged deficiencies in the DfE’s moderation process were subject to different limitation periods and are not time-barred.
Sponsored articles
Walker Morris supports Tower Hamlets Council in first known Remediation Contribution Order application issued by local authority
Generalist Lawyer
Property Solicitor
Locums
01-12-2026
01-12-2026 12:00 pm
To Be Confirmed
To Be Confirmed
To Be Confirmed
To Be Confirmed